A UPS system is one of the most critical components of any mission-critical environment, so before it arrives on site and becomes part of a live electrical infrastructure, it is vital to ensure that it performs exactly as designed.
For this reason, Factory Acceptance Testing (FAT) is an essential component in ensuring the technology performs exactly as promised, and one of the reasons why we encourage our clients to see for themselves the technology performing exactly as promised.

What is FAT and why does it matter?
FAT is the stage where a complete UPS system is assembled, energised and tested within a manufacturing facility. This allows not only our own engineers but also our clients to validate performance under controlled, yet realistic, conditions, ensuring that every component functions as designed.
For any organisation investing in large-scale infrastructure, FAT provides:
• Proof of performance against design specifications
• Early identification of issues, avoiding costly site delays
• Confidence that the UPS will integrate seamlessly with on-site electrical systems
• Verification of resilience, redundancy and fault-tolerance
• Complete transparency between manufacturer, integrator and end user
This is why conducting a Factory Acceptance Test (FAT) before shipment is an industry best practice – and a key part of our own quality assurance process:
Verifies performance against design specifications
FAT confirms that UPS delivers the exact power quality, capacity, efficiency and functionality defined in the technical specification. Any deviation can be identified and corrected at the factory rather than on site, where changes are far more disruptive and costly.
Identifies issues early
Even with world-class manufacturing, complex electrical systems can present unexpected issues. FAT allows engineers to discover and resolve them in a controlled environment. Fixing a problem at the factory avoids delays to the programme, additional labour costs and potential rework during installation.
Ensures system integration and communication work
Modern UPS systems integrate with BMS, DCIM, monitoring platforms, battery systems and switchgear. FAT allows these interfaces, protocols and control sequences to be validated long before installation – ensuring the system will operate seamlessly when commissioned on site.

Provides assurance of mechanical and build quality
A full visual and mechanical inspection confirms that the UPS has been assembled correctly, safely and to the required standard. This includes internal cabling, component fit, airflow paths, accessibility and compliance with relevant regulations.
Demonstrates resilience under simulated real-world loads
Using load banks, the UPS can be tested under a range of load conditions to verify:
• Voltage regulation
• Transfer times
• Redundancy behaviour
• Thermal performance
• Efficiency
This gives all stakeholders confidence that the UPS will maintain power continuity during real operational events.
Reduces risk during installation and commissioning
A successful FAT means the UPS arrives on site with known performance, validated configuration and documented test results. This significantly de-risks the commissioning process and speeds up final integration into the electrical infrastructure.
Builds confidence for all stakeholders
Clients, consultants, contractors and insurers all benefit from the transparency and assurance provided by a FAT. It demonstrates that the system is safe, resilient and ready for deployment – helping protect both the project timeline and the organisation’s mission-critical operations.

Consult with the experts to learn about Factory Acceptance Testing (FAT) and why it matters to your data centre.