Innovative approach and flexible design delivers efficiencies

Birkbeck University of London

Birkbeck University of London traces its history back to 1823. Birkbeck is London’s everything University, providing 20,000 mature students each year with part-time, face-to-face teaching in the evenings. In common with many educational establishments, academic departments have often led the College’s IT development.

As a result, Birkbeck has found itself with four separate, small equipment rooms with their own cooling and UPS, each providing services to specific College departments.

Requirement

As one of Birkbeck’s four rooms would have to be vacated due to the extent of the electrical work, the University decided there was an opportunity to consolidate the IT infrastructure.

David Willcox, IT Infrastructure Manager, commented: “One of the other rooms was no longer fit for purpose; it had evolved and was beyond its sell-by date.

There was a clear opportunity to rationalise, consolidate and create a single, state-of-the-art data centre to support Birkbeck’s future IT requirements.

The college also wanted to take the opportunity to improve data centre efficiency and drive down energy consumption as far as possible.

“Birkbeck has a responsibility to act with due diligence and is committed to carbon reduction,” Willcox added.

“The development of this new data centre would have happened anyway; but it also provided an opportunity to exploit innovative data centre designs wherever possible to maximise efficiency and reduce energy usage.”

It was therefore essential to work with a data centre provider that could guarantee that the delivery would be on time. Birkbeck turned to data centre expert 2bm based on a strong track record in delivering diverse data centre requirements.

Challenge

“Following the tender process, it was clear that 2bm was the only company willing and able to take into account the specific challenges associated with this data centre space,” added Willcox.

The primary challenge for 2bm was the delivery of 56 cabinets with a design of 240kW technical load, together with all the facilities support infrastructure required within a minuscule 180m2 of floor space, and a low floor ceiling height of 3.1m.

While the College has, for the first time, a single dedicated space in which to create a state-of-the-art data centre, the project was far from straightforward.

The new space was pretty small for the number of racks required, and it is also in the centre of the building, surrounded by other spaces undergoing redevelopment.

David Willcox said: “This was a complex project, not least because the vacation of the building meant there was a specific deadline for the first phase.”

“This project required a lot of interaction with the other building work that was going on and therefore required a supplier capable of being extremely flexible as well as committed to meeting our deadlines,” added David.

Result

This focus on energy efficiency has resulted in an overall reduction in power consumption. Indeed, this new data centre is projected to have a PUE rating in the region of 1.3.

Critically, however, the data centre will now support the college’s ongoing provision for technology.

Willcox commented: “The reliance upon IT within Birkbeck cannot be understated.”

“We have to be as flexible and reactive in terms of the IT requirements of our teaching staff and researchers as possible and anything that provides better protection and an improvement in performance and availability is incredibly valuable.”

Indeed, the new space enables Birkbeck to explore other avenues, including adopting desktop virtualisation, which will demand additional data centre equipment.

Testimonial

We selected 2bm based on their technical expertise and excellent reputation in data centre design and installation. 2bm has been extremely helpful, managing the project from start to completion with no challenge too great.

We knew this would be a complicated project with a range of challenges which would need to be overcome. 2bm approached these with ease and have been able to complete the project on time and within budget.

David Willcox – IT Infrastructure Manager

Other case studies

Would you like to know more?

Please contact us to speak to a member of our team or to arrange a free site survey.

Contact Us Footer

  • This field is for validation purposes and should be left unchanged.
©2bm Limited 2026
Managed by We are Kudos